Amazing work
I’m trying now to colorize the 3D View Visual based on the planned date & actual date as there are 4 scenarios,
-
(no data entered): both the planned date & actual date have no values and the corresponding piles to be yellow color.
-
(done): actual date has a value equal to or less than another conditional parameter we can call it (Data date)
regardless of the planned date value. -
(delayed): The planned date has a value less or equal to the data date, and the actual date has no value.
-
(ahead): The planned date has a value greater than the data date, and the actual date has no value.
I can not create a conditional format based on dates in color by option.
is there any workaround?